Inspection Request Codes

-A A +A

PLEASE NOTE CHANGE IN INSPECTION SCHEDULE:  Cut off time for scheduling inspections is being changed from 7:30 AM the day of requested inspection to 4:00 PM the day before. This change will take effect on November 23, 2015.

In order for us to more efficiently provide you with the inspection service you need, please request inspections utilizing the codes and types shown below. If you need an inspection that fits none of the types listed, call 407-585-1360/1361.
Building Electric Plumbing
Mechanical Fire Pools
Aluminum Enclosures   Additional Explanations

Building

B101

Footing (Stemwall-Type Construction and/or Column Pads)

B102

Slab (Pre-Pour)

B103

Mono-Slab **

B104

Lintel/Tie Beam/Fill Cell/Cast-in-Place Col./Beam/Rebar Downcell

B105

Roof Sheathing (Decking)

B106

Framing (Includes Window and Door Fastening)

B107

Wall Sheathing and Strapping

B108

Ceiling Air Barrier (Commercial)

B109

Tilt Wall

B110

Windows/Doors (Stand Alone)

B111

Insulation

B112

Insulation Roof (Commercial)

B113

Rated Assembly Fastening

B114

Rated Assembly Penetrations

B115

Building Ceiling Cover

B116

Roof Dry-In

B117

Pre Pour Driveway and/or Sidewalk

B118

Trailer Blocking and Tie Downs

B119

Sign Fastener Inspection

B120

Sunroom Framing

B121

Final Fence

B122

Final Sign

B123

Final Building

B124

Final Shed

B125

Final Driveway

B126

Final Sidewalk

B127

Final Demo

B128

Final Tent

B129

Final Roof

B130

Final Pool Enclosure/Screen Enclosure/Screen Room/Sunroom

B131

Miscellaneous Building

Electric

E201

Temp Power

E202

U/G Electric

E203

Rough Electric (commercial)

E204

Rough Electric (residential)

E205

Rough Fire Alarm

E206

(Reserved)

E207

Ceiling Electric

E208

Ceiling Fire Alarm

E209

Rough Low Voltage

E210

Final Low Voltage

E211

Pre-Power

E212

Meter Set (Residential)

E213

(Reserved)

E214

Final Electric

E215

Final Sign Electric

E216

Misc Electric

Plumbing

P301

Plumbing U/G and H2O Pressure Test

P302

2nd Rough Plumbing and Water Piping Pressure Test

P303

Penetrations of Rated Systems (Commercial)

P304

(Reserved)

P305

Sewer/Septic Tie-In

P306

(Reserved)

P307

Plumbing Ceiling Cover (Commercial)

P308

Final Plumbing

P309

Re-Pipe Final

P310

Irrigation

P311

Solar Heat System Final

P312

Gas Piping Pressure Test

P313

Rough Gas Pressure Test (After Drywall)

P314

Final Gas/Manometer/Hook-Up

P315

Misc Plumbing

Mechanical

M401

Rough Mechanical (Includes Penetrations of Rated Systems-Commercial)

M402

HVAC Duct

M403

HVAC Duct Wrap/Firewrap/Insulation

M404

Fire Damper Framing

M405

Mechanical Ceiling Cover

M406

Grease Duct Weld

M407     (Reserved)

 

M408

Hood

M409

Condensate Lines

M410

Roof Top Unit Fastening

M411

Chill Water Piping

M412

Final Mechanical

M413

Refrigerant Piping Test

M414

Smoke Shut Down

M415

Misc Mech

Fire

F501

Sprinkler U/G Visual

F502

Sprinkler U/G Conduit

F503

Sprinkler U/G Hydro

F504

Sprinkler U/G Flush

F505

Hydrant Flow/Flush Test

F506

Sprinkler Hanger

F507

O/H Hydro 2 HR Test

F508

Pre-Action Hydro Test

F509

Pre-Action Air Test

F510

Dry System Air Test/24 HR.

F511

Final Sprinkler    

F512

FM200 Acceptance Test**

F513

Halon 1301 Test

F514

Misc Fire

F515

Exit Lighting Rough-In

F516

Smoke HVAC Test

F517

HVAC Shutdown Test

F518

ANSUL/Hood System Test**

F519

Rough Alarm

F520

24 HR Battery Test---Start

F521

24 HR Battery Test---End

F522

Alarm Acceptance Test/Final Alarm

F523

Fire Pump Acceptance Test**

F524

Fire Pre Power**

F525

Courtesy Fire Final---Subject to Schedule

F526

Final Fire

F527

(Reserved)

F528

Mag Lock/Access Control/Delayed Egress Test**

F529

Gate/Siren Inspection

F530

Sprinkler O/H Visual

F531

U/G Fire Line

Pool

B132

Steel & Ground (Pool Main Drain Piping Also Required P316)

P316

Pool Main Drain Piping (Steel & Ground Also Required B132)

B133

Pool Retaining Wall Footing

B134

Pool Retaining Wall Lintel/Fill Cell

E217

Pool Underground Electric (U/G Plbg Also Required P317)

P317

Pool Underground Plumbing (U/G Electric Also Required E217)

B135

Pool Deck

B136

Pool Final (Pool Final Electric Also Required E218)

E218

Pool Final Electric (Pool Final Also Required B136)

E219

Light Niche Bonding

Aluminum Enclosures

B120

Sunroom Framing/Fastener Inspection**

B130

Final Pool Enclosure/Screen Enclosure/Screen Room/Sunroom

Additional Explanations**

B103

Mono Slab-Refers to the type of construction where perimeter and interior footings are poured integrally with the slab.

B108

Ceiling Air Barrier-Refers to the Energy Code required barrier at the ceiling when the thermal envelope of the building is the ceiling. House wraps and taped and sealed dry wall may constitute a air barrier but dropped acoustical tile ceilings may not. See FBC Chapter 13 SubChapter 2 for definition.

B112

Insulation Roof (Commercial)-In composite roof applications where insulation is part of the assembly the insulation is present to satisfy energy code requirements and must be verified. This can be an in-progress inspection. Coordinate with the building department.

B116

Roof Dry In-Valley lining, drop edge, roof vents, and flashing shall be installed at time of inspection.

B118

Trailer Blocking and Tie Downs-Tie down and electrical inspection are required before power will be released for construction trailers. Plumbing or Mechanical systems not self-contained with the trailer package require separate permits.

B119

Sign Fastener Inspection (Wall Signs)-Inspection of attachment and fasteners is required in the City of Lake Mary. Coordinate the building department inspection with your installation to provide access and inspection of attachment locations.

B120

Sunroom Framing/Fastener Inspection-Required in applications where major connections will be concealed when the wall assembly is completed. This inspection is to take place while the wall assembly is open. Call for inspection per regular procedure and, if desired, coordinate an in-progress inspection by calling inspection staff between 8am and 8:30 am on the day of the inspection.

B122

Final Sign-When sign is a wall sign coordinate final sign inspection with final sign electric inspection.

E211

Pre-Power Commercial-Both Electrical and Fire Pre-Power inspections are required for the release of power to the building.

F512

FM200 Acceptance Test-Includes cylinder pressure test, door fan test, and smoke detector checks, fire alarm tie-in, purge panel and purge system inspection.

F518

ANSUL/Hood System Test-Should be done in conjunction with the mechanical (HVAC) contractor and fire alarm company at the time of acceptance test.

F523

Fire Pump Acceptance Test-Done in conjunction with the fire pump manufacturer’s representative. (Fire alarm company to be present at time of inspection.)

F524

Fire Pre-Power-Both Fire Pre-power and Electrical Pre-Power inspections are required for the release of power to the building.

F528

Mag Lock/Access Control/Delayed Egress Test-Acceptance of magnetic-type locks requires the presence of the fire alarm company